| Location | Nong Bua, Nakhon Sawan |
| Owner | SCG Cement Co.,Ltd. |
| Employer | SCG Cement Co.,Ltd. |
| Total Quantity | 1,970,000 tons |
| Contract Period | 2012-2018 |
| Project progress | Finished |
| Role | Main contractor |
| Project description | Overburden removal, drilling & blasting, excavating & hauling and crushing at capacity 450 tph. |